11/1/22 UPDATE: On Wednesday, November 2nd, the City paved Arquilla Drive, Eliza Street, and Buchanan Street (partially)
11/2/22 UPDATE: On Thursday, November 3rd, the City paved Buchanan Street (partially), North Elm Street, and Willow Street.
11/3/22 UPDATE: On Friday, November 4th, the City paved Bayview Avenue, Kitteridge Place, Stratford Place, Harborview Court, and part of Hudson Avenue.
11/4/22 UPDATE: On Monday, November 7th, the City paved Hudson Avenue, Dennings Avenue (between 9D and Hudson Avenue), Coffey Avenue, Aldridge Place, Beskin Place, and began work on Sycamore Drive.
11/7/22 UPDATE:
– On Tuesday, November 8th, the City paved Dennings Avenue (from Hudson Avenue to the Wastewater Treatment Plant), finished work on Sycamore Drive, and completed Jefferson Avenue, Pleasant View Avenue, and Glenford Avenue.
– On Wednesday, November 9th, the City paved East Street, Center Street, Masters Place, and began work on Mase Street.
11/9/22 UPDATE:
– On Thursday, November 10th, the City paved Mase Street, Boyce Street, Depuyster Avenue, and began work on Roundtree Court.
– On Monday, November 14th, the City paved the remainder of Roundtree Court.
11/14/22 UPDATE:
Earlier today, the City completed the last of the repaving for the large-scale street resurfacing project that took place throughout the month of November.